SILLENO — ECU Heater Island Piping Works

SILLENO — ECU Heater Island Piping Works

Prefabrication of Pipe Spools (CS, SS, Alloy), Pipe Support, Painting, Site Erection of Spools, Installation of Supports, Hydrotest and Insulation for HEATER ISLAND,

SCOPE OF WORK

  • 132,401 Dia Inch Pipe Spool Prefabrication (0.75" - 78")
  • 272 Ton Pipe Support Prefabrication
  • 120,000 Dia Inch Pipe Erection on Site
  • 285 Ton Pipe Support Installation
  • 45,000 meter Insulation
  • PFP
Location

Karabatan

Completion Year

2028

Client

TECNICAS REUNIDAS & Sinopec JV